TNEI on Grid – New Year, New Process
The energy industry is now on the verge of a significant change, with 2025 bringing the implementation of Connections Reform in Great Britain (GB). On 20th December, NESO submitted two CUSC Final Modification Proposals to Ofgem for approval for CMP 434: Implementing Connections Reform, and CMP 435: Application of Gate 2 Criteria to existing contracted background. Why change? The GB Connections Reform proposals have been developed to address the rising number of generators waiting to connect to the grid – often referred to as the “connections queue”. Under the current ‘first come, first served’ process, the rate of connection applications has far exceeded the pace at which the NESO, Transmission Owners (TOs), and Distribution Network Operators (DNOs) can get projects connected to their networks, leading to a backlog of generation in the queue far greater than will be needed to meet the country’s energy demands by 2050. CMP 434 – Looking