TNEI on Grid: Great Britain’s Connections Reform – The Story So Far
The GB electricity industry is undergoing fundamental change, to such an extent that almost everything will be different by 2030 – assuming the country’s Net Zero plans are delivered. In the grand scheme of the change and uncertainty, proposals to reform the connections processes in GB sounds trivial but we believe it is one of the most influential initiatives that will practically affect (help or hinder) delivery of Net Zero. But why is this? With the move away from ‘First-Come, First Served’ to ‘First-Ready, First Connected’, the GB Connections Reform (GBCR) project being run by ESO, is changing the key principles under which the industry connects new projects to the grid. This is the first in a series of papers by TNEI to help explain what these changes are, how they’ll impact you, and how we can help. How does Grid Connection affect project deliverability? The earliest reference we could