TNEI on Grid – Connections Reform Timeline Published
Don’t risk losing out on your place in the connections queue, all evidence must be submitted before 29th July 2025. Last week (10th June), NESO published the timeline for the delivery of connections reform in Britain. The timeline includes key dates for projects looking to progress to a Gate 2 offer as part of the Gate 2 to whole queue (G2TWQ) process, under CMP (Code Modification Proposal) 435: Application of Gate 2 Criteria to existing contracted background. Figure 1: NESO Connections Reform Timeline The key milestones TNEI has identified for projects passing through G2TWQ include: 20th May 2025 – DNO Evidence Submission Opens. Small and medium embedded generators are now able to submit their evidence of meeting the Gate 2 requirements to their relevant DNO. Depending on the DNO evidence is either submitted via email using the NESO Readiness Declaration template or through an online portal. 8th July 2025 –