TNEI on Grid – Evidence Extension, Portal Problems and Submission Support
The Gate 2 evidence submission window has been extended following an announcement from NESO on Friday (25th July). All projects will now have up until at least the 18th August to submit their Gate 2 evidence to NESO or their relevant DNO. The Story So FarThe DNO evidence submission window has been open since 20th May 2025. This was followed by the NESO submission window which opened on the 8th July, with both windows originally due to close on 29th July. However, on 16th July NESO announced that it would be extending the evidence submission window by a further 5 working days due to a significant number of problems faced by users attempting to submit evidence through the NESO portal. On Friday last week (25th July) NESO announced that the submission window is to be further extended. NESO intend to provide notice of the window closure 10 working days in