Technical due diligence for portfolio acquisition

TNEI undertook technical due diligence of a portfolio of 14 onshore wind farms in Northern Ireland and the Republic of Ireland, some in construction phase and others in operational phase, totalling 221MW. The review comprised a Phase 1 Red Flag Review and Phase 2 Detailed Review of grid connection, electrical infrastructure, planning, consenting, health and safety, noise and shadow flicker aspects. TNEI was subcontracted to K2 Management, who was responsible for delivering the wider due diligence review to CGN. Following successful completion of the due diligence works; CGN acquired a proportion of the portfolio.

Find out more about the project here